Basotho people demand compensation for Lesotho Dam construction, 2001-2005.

Goals

Residents demanded compensation for their land taken for the Lesotho Highlands Water Project.

Time period notes

Residents likely began campaigning for compensation around 1996, though no direct actions are on the record until 2001.

Time period

November, 2001 to March, 2005

Country

Lesotho

Location City/State/Province

Katse, Mohale, Maseru

Location Description

communities impacted by dam construction and capital city
Jump to case narrative

Methods in 1st segment

  • One thousand gathered at the Mohale Dam, blockading access roads with stones.

Methods in 4th segment

  • In 2003, the Ombudsman released a public report outlining the complaints of communities affected by LHWP dam construction.

Methods in 6th segment

  • In March 2005, the World Bank released a report, stating that the LHWP’s first phase did not comply with treaty requirements regarding resettlement and community development.

Segment Length

6 months

Notes on Methods

It is unclear what methods the residents used in segments 2-5.

Leaders

Residents impacted by the Katse and Mohale Dams (Survivors of the Lesotho Dams)

Partners

Transformation Resource Centre, International Rivers

External allies

not known

Involvement of social elites

Ombudsman Office

Opponents

Lesotho Highlands Development Authority

Nonviolent responses of opponent

not known

Campaigner violence

not known

Repressive Violence

Police repressed protesters with batons and whips, causing three elderly women to require medical attention. In the capital city Maseru, police denied demonstrators a permit to gather.

Cluster

Human Rights

Classification

Defense

Group characterization

villagers
local farmers

Groups in 1st Segment

Transformation Resource Centre
International Rivers (enter)

Groups in 4th Segment

Ombudsman Office

Segment Length

6 months

Success in achieving specific demands/goals

2 out of 6 points

Survival

0.5 out of 1 points

Growth

2 out of 3 points

Total points

4.5 out of 10 points

Notes on outcomes

Though the LHDA did address some of the residents' grievances, it is unclear whether they provided all delayed compensation to the residents. It does not seem that the residents were satisfied by the LHDA's actions.

Database Narrative

 In 1986, the national governments of South Africa and Lesotho jointly launched the Lesotho Highlands Water Project (LHWP).  The Project would involve the construction of several large dams, tunnels, bridges, and power lines, in an effort to transport water from Lesotho to South Africa and to produce electricity. 

In 1990, the LHWP, estimated to cost $16 billion, became the largest World Bank-funded initiative in sub-Saharan Africa.  The two countries established the Lesotho Highlands Development Authority (LHDA) to oversee the completion of the 30-year project.  The mandate of the LHDA included an expectation that the LHWP should benefit the economy of Lesotho without decreasing the quality of life for any residents.

In 1990, the LHDA began power-line construction for the Water Project, displacing a number of families. The LHDA promised an annual payment for 15 years for residents losing their land. A 1993 LHDA survey showed that residents were unsatisfied with the amount of compensation to be provided, stating that it did not match the productive value of their land. In 1995, those families remained without compensation or replacement housing.

In 1998 the LHDA began Phase 1 of the project with construction of the Katse Dam, the largest dam in Africa, followed by the Mohale Dam and Muela Dam.  20,000 people came from elsewhere to work for the LHWP. The International Rivers Network reported that these temporary workers spread HIV/AIDS in the area.  

The three projects displaced 467 households and affected thousands more, through the flooding of villages, fields, and grazing lands. The LHWP relocated or resettled 2,000 residents who the flooding had directly displaced. As of 1998, the LHDA had provided none of the displaced residents with compensation.  The LHDA supposedly allocated additional funds to local governments for development projects, but residents claimed that corrupt officials had not released those funds.

Resettlement required residents to shift their dependence from subsistence agriculture to cash. The need for resettlement only exacerbated the poverty.  Resettled residents henceforth had to pay for water through public utilities, since the water they previously held in common had been dammed.  

After its completion, the Katse Dam, due to its immense weight, caused a series of earthquakes in the surrounding area.  The LHDA relocated residents impacted by these earthquakes to low-quality storage-shed housing. The Transformation Resource Center and the Highlands Church Action Group helped affected residents to communicate their complaints to the LHDA.  

On 19 November 2001, over two thousand demonstrators marched and sang in protest of the persistent negative impacts of the dams.  The marchers claimed that the LHDA had not fairly compensated them for their lost land. The protesters demanded a ten-percent share of royalties from the projects, a formal inquiry into the dams’ negative effects, and an extension of the 15-year compensation period.  Protesters delivered a petition with their demands to the LHDA and claimed that the LHDA had ignored complaints made through institutional channels.  

About one thousand gathered at the Katse Dam. Another thousand gathered at the Mohale Dam, blockading access roads with stones.  Police repressed these protesters with batons and whips, causing three elderly women to require medical attention.  

About three hundred demonstrators gathered at the Muela Dam; others attempted to assemble in the capital city Maseru.  Police did not grant permission for the Maseru demonstration.  

Representatives from the Transformation Resource Center, including Motseoa Senyane, acted as spokespeople about the demonstrations for international media. The non-governmental organizations International Rivers and the Environmental Monitoring Group also expressed their support for the protesters.  

Since the dams’ construction, the Ombudsman, holding the position responsible for processing grievances about public agencies, received many complaints from the people who the LHDA had resettled. In 2003, the Ombudsman conducted a public inquiry into the many complaints that had been lodged with his office by residents impacted by the LHWP.

Later that year, the Ombudsman released a public report. 

In March 2005, the World Bank released a report, stating that the LHWP’s first phase did not comply with treaty requirements regarding resettlement and community development.  On 4 October 2005, 500 impacted residents, calling themselves the Survivors of the Lesotho Dams, marched in Maseru, reiterating demands for adequate compensation, development and training, and sanitation in resettled communities.  They called on the government to halt further progress on the LHWP, until addressing outstanding grievances.  Chairperson of the group the Survivors of the Lesotho Dams, Monaheng Mahlakeng, acted as a spokesperson for media.  The Transformation Resource Center and International Rivers Network made statements in support of this demonstration.

Over time, the LHDA addressed some of the residents’ grievances.  The LHDA extended the compensation period to 50 years and released delayed communal compensation to affected communities.  In 2005, after claiming financial inability to pay annual compensatory stipends, the LHDA agreed to pay those stipends.  

The marches in 2005 that gained concessions by the LHDA marked the end of the use of nonviolent direct action in the people’s campaigning for fair treatment.

The project as a whole continued to be built.  In August 2011, the LHDA launched the second phase of the LHWP, beginning construction of the Polihali Dam.  The LHDA expects to complete this project by 2018 and predicts that about 4,000 households will be impacted.

The period since 2005 has been marked by some continued efforts to gain fuller compensation for displaced people, such as the pressure in 2006 by the Transformation Resource Center which achieved a long-delayed resettlement house for the Lakabane family. The Ombudsman’s office also continued to speak out. The office in 2010 released another report explicitly holding the LHDA responsible for the grievances of the residents, including that of delayed compensation.

Influences

not known

Sources

“Muela Dam.” The Orange-Senqu River Basin Infrastructure Catalogue, ORASECOM Report. 2013. http://wis.orasecom.org/content/study/UNDP-GEF/InfrastructureCatalogue/Documents/Reservoirs/Muela%20Dam.pdf

“Huge Protest Over Large Dams in Lesotho- Police Attempt to Disrupt Demonstrations, Injuring Three.” 27 Nov 2001. International Rivers. http://www.internationalrivers.org/pt-br/resources/huge-protest-over-large-dams-in-lesotho-police-attempt-to-disrupt-demonstrations-injuring

“Earthquakes Triggered by Africa’s Katse Dam Force Families to Abandon Damaged Village.” 10 Feb 1997. International Rivers. http://www.internationalrivers.org/resources/earthquakes-triggered-by-africa-s-katse-dam-force-families-to-abandon-damaged-village-3860

“The Dammed: Five Controversial Dams: Lesotho/South Africa.” 18 Sept 2003. Wide Angle. http://www.pbs.org/wnet/wideangle/episodes/the-damned/five-controversial-dams/lesothosouth-africa/3106/

Hildyard, Nicholas. “The Lesotho Highland Water Development Project- What Went Wrong?” 10 July 2002. The Corner House. http://www.thecornerhouse.org.uk/resource/lesotho-highland-water-development-project-what-went-wrong#appendix-01-10-00-00

Devitt, Paul and Hitchcock, Robert K. “Who Drives Resettlement? The Case of Lesotho’s Mohale Dam.” July 2010. African Study Monographs, 31(2): 57-106. http://jambo.africa.kyoto-u.ac.jp/kiroku/asm_normal/abstracts/pdf/31-2/31-2.pdf

“Lesotho: Dam-building continues despite controversy.” IRIN. http://www.irinnews.org/report/94169/lesotho-dam-building-continues-despite-controversy

“Lesotho: Protests over dam expansion.” Pambazuka News. 224. 4 Oct 2005. http://pambazuka.org/en/category/environment/29680


Office of Ombudsman in Lesotho. The three Ombudsman reports The first report is called Ombudsman Report  on Mohale Sitting- Lowlands, 2003;  Ombudsman Report on Mohale Inquiry, 2006 and Ombudsman Report on Katse Inquiry-Mphorosane, 2010.

Moeletsi oa Basotho. Editorial section. February, 2000.

Name of researcher, and date dd/mm/yyyy

Katleho Khang 06/03/2013 and Laura Rigell 30/07/2014